Open a self-service laundromat in Singapore

How to open a self-service laundromat in Singapore

Last reviewed: 22 Nov 2026 · Editorial standards

A laundromat needs no special business licence that we could find, but location is the hard part: URA does not allow laundromats in industrial buildings or homes, and HDB shops need a change of use that is not guaranteed. Plan early for PUB’s rules on discharging washing water and for heavy electrical works by a licensed electrical worker. This guide puts every step in order with official sources.

Build my opening plan

~19 weeksfrom a standing start (default assumptions)
21steps
14official sources checked

Decide and register

  1. 1Decide your location type, machine mix and pricing

    Laundromats do best near dense housing and dormitories. Decide your machine mix (washers, dryers, large-load machines) and pricing per cycle.

    Typical lead time
    Allows 7 days. Planning estimate
    Gather
    • Target area
    • Machine mix
    • Price per wash and dry
  2. 2Set your budget and break-even

    Machines are the largest upfront cost; water and electricity are the largest running costs. Work out cycles per day needed to break even.

    Typical lead time
    Allows 7 days. Planning estimate
    Gather
    • Funding available
    • Break-even cycles per day
  3. 3Register your business with ACRA

    Register through Bizfile.

    Typical lead time
    Allows 3 days. Planning estimate
    Gather
    • Business name options
    • Owner details
    • Business address

    ACRA lists a one-year sole proprietorship registration at $115 ($15 name application plus $100 registration).
    ACRA: Choosing a business structure (checked 22 Nov 2026)

    Not a Singapore Citizen or PR? Starting a business as a foreigner →

  4. 4Open a business bank account

    Cashless payment providers settle into a business account.

    Typical lead time
    Allows 14 days. Planning estimate

    How to open a business bank account →

  5. 5Check whether you must register for GST

    Compare your revenue forecast with the IRAS threshold.

    Typical lead time
    Allows 2 days. Planning estimate

    GST registration is compulsory if taxable turnover exceeds $1 million at the end of a calendar year, or is expected to in the next 12 months.
    IRAS: Do I need to register for GST? (checked 25 Nov 2026)

    GST registration and business tax basics →

Premises

  1. 7Check water, drainage and power

    Commercial washers and dryers need water inlets, floor drainage to the sewer, ventilation for dryer exhaust and enough electrical load.

    Typical lead time
    Allows 7 days. Planning estimate
    Confirm with

    Landlord

    • Water inlet and drainage points
    • Dryer exhaust route
    • Available electrical load
    • Reinstatement at lease end
  2. 8Negotiate and sign the lease

    Ask for an exit clause if URA or HDB approval is refused, and allow rent-free time for approvals and installation.

    Typical lead time
    Allows 14 days. Planning estimate
    Confirm with

    Landlord

    • Exit clause if approval is refused
    • Rent-free period
    • Permission for 24-hour operation

Approvals

  1. 9Get URA or HDB approval for a laundromat

    HDB shops apply to HDB; commercial buildings apply to URA (check instant lodgment first); eligible shophouses can lodge for instant approval.

    Typical lead time
    Allows 30 / 3 / 14 days for HDB / shophouse lodgment / commercial. Planning estimate

    HDB processes a change of use in at least 4 weeks after all documents and payment are received; tenants of HDB rental shops apply through GoBusiness.
    HDB: Change of use: application process (checked 25 Nov 2026)

    URA’s change of use fee is $500 (non-refundable) and assessment generally takes 10 working days; URA advises not to commit to a tenancy or renovation before its decision.
    URA: Changing the use of your property (checked 25 Nov 2026)

  2. 10Plan electrical works with a licensed electrical worker

    Dryers and washers draw heavy loads. A licensed electrical worker designs and certifies the installation, and larger loads need an EMA installation licence.

    Typical lead time
    Allows 14 days. Planning estimate

    EMA requires electrical works at consumers’ premises to be done by Licensed Electrical Workers, who inspect and certify the installation before supply is turned on.
    Energy Market Authority (EMA): Electrical safety (checked 25 Nov 2026)

    EMA requires an electrical installation licence for non-domestic installations with an approved load above 45 kVA.
    Energy Market Authority (EMA): Electrical installation licence (checked 25 Nov 2026)

  3. 11Check whether SCDF plans are needed

    Ask a Qualified Person whether your change of use or works affect fire safety and need SCDF approval.

    Typical lead time
    Allows 14 days (planning assumption). Planning estimate

    SCDF requires plan approval before fire safety works or a change of use affecting fire safety, submitted by a Qualified Person; works under the Fire Safety (Exemption) Order need no submission.
    Singapore Civil Defence Force (SCDF): Plan approval (checked 25 Nov 2026)

  4. 12Check PUB rules for discharging washing water

    Ask PUB whether your laundromat needs written approval to discharge used water to the sewer. If it does, apply early — it takes 4–6 weeks.

    Typical lead time
    Allows 35 days in case approval is needed. Planning estimate

    PUB requires trade premises that discharge trade effluent into the public sewer to obtain its written approval first; discharging without it is an offence.
    PUB: Trade effluent management (checked 25 Nov 2026)

    PUB’s written approval has no application fee, takes 4–6 weeks (30 working days) after a complete submission, and is valid for 5 years; monthly fees apply if effluent exceeds the limits.
    GoBusiness Licensing: Written approval for the discharge of trade effluent into the public sewer (checked 25 Nov 2026)

Fit-out

  1. 13Fit-out: plumbing, drainage, ventilation and seating

    Plumbing and drainage for every machine, dryer exhaust ducting, electrical works, lighting, folding tables and seating.

    Typical lead time
    Allows 21 days. Planning estimate
    Confirm with

    Contractor

    • Plumbing and drainage per machine
    • Dryer exhaust ducting
    • Completion date
  2. 14Signage and usage instructions

    Outside signage, plus clear instructions, prices and an emergency contact number inside.

    Typical lead time
    Allows 10 days. Planning estimate

    BCA exempts signboards totalling not more than 5m²; licence applications take about 7 working days, plus two weeks if URA must evaluate.
    BCA: Outdoor advertising sign / signboard licence application (checked 22 Nov 2026)

Machines and systems

  1. 15Order commercial washers and dryers

    Commercial washers, dryers and large-load machines. Check water use, servicing and spare parts.

    Typical lead time
    Allows 30 days. Planning estimate
    Confirm with

    Machine supplier

    • Delivery and installation lead time
    • Water and power requirements
    • Servicing and warranty

    PUB’s water-efficiency guide for commercial laundries is recommended rather than mandatory; recycled wastewater must still meet trade effluent limits.
    PUB: Best practice guide in water efficiency: commercial laundry sector (PDF) (checked 25 Nov 2026)

  2. 16Set up cashless payment and remote monitoring

    Cashless or app payment, a coin or note changer if needed, CCTV and remote monitoring for an unmanned shop.

    Typical lead time
    Allows 10 days. Planning estimate

People and compliance

  1. 17Recruit part-time staff

    Applies if Will the shop be staffed? Staffed for some hours

    Staff for cleaning, customer help and wash-and-fold services.

    Typical lead time
    Allows 21 days. Planning estimate

    Employers pay CPF for Singapore Citizen and PR employees earning more than $50 a month.
    CPF Board: How much CPF contributions to pay (checked 25 Nov 2026)

    Hiring your first employee: employer checklist →

  2. 18Arrange insurance

    Public liability, machine breakdown, fire and contents cover; work injury compensation if you hire staff.

    Typical lead time
    Allows 7 days. Planning estimate

    Which insurance is required, and what to consider for your sector →

Launch

  1. 19Google listing, website and opening promotion

    Most customers search “laundromat near me”. Set up your Google Business Profile and a simple website with prices and hours.

    Typical lead time
    Allows 14 days. Planning estimate
  2. 20Install machines and test every cycle

    Install, connect and test every machine and payment flow; the electrical worker certifies the installation.

    Typical lead time
    Allows 5 days. Planning estimate

Costs to budget for

Costs to budget for
UpfrontPlanning range
Security deposit (assumed 3 months’ rent)S$7,500 – S$21,000
Plumbing, electrical works and fit-outS$15,000 – S$50,000
Commercial washers and dryersS$40,000 – S$90,000
Payment system, CCTV and monitoringS$3,000 – S$10,000
URA/HDB and professional feesS$500 – S$4,000
ACRA registrationS$115 – S$700
Signage and opening promotionS$1,500 – S$5,000
Insurance (first-year premium)S$800 – S$2,500
MonthlyPlanning range
Rent (incl. service charge)S$2,500 – S$7,000
Water and electricityS$1,500 – S$5,000
Cleaning, detergent vending stock and maintenanceS$300 – S$1,200
Payment and monitoring subscriptionsS$100 – S$500
MarketingS$100 – S$600
Accounting and bookkeepingS$200 – S$600

Planning estimate Planning estimates by OpenReady SG, last reviewed 22 Nov 2026. They are not quotes or published prices — replace them with your own quotes.

Budget calculator →

What changes your plan

What kind of premises?
URA and HDB treat laundromats differently by building type; some shophouses can use URA’s instant lodgment.
How many machines?
Changes machine cost, electrical load and water use.
Will the shop be staffed?
Most laundromats run unmanned with remote monitoring; staffed shops can add wash-and-fold services.

Official sources