Open a café in Singapore

How to open a café in Singapore

Last reviewed: 22 Nov 2026 · Editorial standards

Most of the time in a café opening goes on things that must happen in order: you cannot finalise a layout without premises, apply for your food shop licence without a layout plan, or train staff without equipment. This guide lists every step in the order it usually happens, with the lead time we assume and the official page for each regulatory step. Use the plan builder to turn it into dates for your own opening.

Build my opening plan

~25 weeksfrom a standing start (default assumptions)
29steps
13official sources checked

Decide and register

  1. 1Define your concept, menu and customer

    Decide what you sell, who buys it, average spend and opening hours. Every later decision (location, kitchen, equipment) depends on this.

    Typical lead time
    Allows 10 days to settle concept and menu. Planning estimate
    Gather
    • Draft menu with target prices
    • Target customer and peak hours
    • Seating count you need
    • Three comparable cafés and their prices
  2. 2Set your budget, funding and 12-month cash flow

    Use the budget tool to separate upfront, monthly and contingency costs, then confirm how it will be funded.

    Typical lead time
    Allows 7 days to build the budget and confirm funding. Planning estimate
    Gather
    • Personal and partner contributions
    • Loan or grant terms if any
    • Break-even daily sales estimate
  3. 3Register your business with ACRA

    Register a sole proprietorship, partnership or company through Bizfile. Licences, leases and bank accounts usually need the registered entity.

    Typical lead time
    Allows 3 days for name approval and registration. Planning estimate
    Gather
    • Proposed business name (and a backup)
    • Owner / director NRIC or passport details
    • Registered business address
    • Business activity (SSIC) description

    ACRA lists a one-year sole proprietorship registration at $115 ($15 name application plus $100 registration).
    ACRA: Choosing a business structure (checked 22 Nov 2026)

    Not a Singapore Citizen or PR? Starting a business as a foreigner →

  4. 4Open a business bank account and set up bookkeeping

    Keep business and personal money separate from day one; deposits and supplier payments will need it.

    Typical lead time
    Allows 14 days for bank onboarding. Planning estimate
    Gather
    • ACRA business profile
    • ID of all owners/directors
    • Accounting software choice

    How to open a business bank account →

  5. 5Check whether you must register for GST

    Registration is compulsory once taxable turnover passes the IRAS threshold. Most new cafés start below it, but check your forecast.

    Typical lead time
    Allows 2 days. Planning estimate

    GST registration is compulsory if taxable turnover exceeds $1 million at the end of a calendar year, or is expected to in the next 12 months.
    IRAS: Do I need to register for GST? (checked 25 Nov 2026)

    GST registration and business tax basics →

Premises

  1. 7Run premises checks before you sign

    Check services and constraints that are expensive to fix later: power load, water and drainage, exhaust route, grease trap, fire exits and the landlord’s fit-out rules.

    Typical lead time
    Allows 10 days for site checks and contractor walk-throughs. Planning estimate
    Gather
    • Floor plan with dimensions
    • Landlord fit-out manual or rules
    • Photos of DB box, water points and ceiling
    Confirm with

    Landlord

    • Available electrical load (amps / phases)
    • Grease trap location and whether shared
    • Rent-free fit-out period
    • Reinstatement obligations at lease end

    Contractor or designer

    • Rough fit-out cost for this unit
    • Whether works need a Qualified Person (QP)

    PUB requires kitchens of cafés, restaurants and similar outlets to install grease traps; outlets without cooking may be exempted with PUB’s permission.
    PUB: Frequently asked questions — used water (PDF) (checked 22 Nov 2026)

    Full premises checklist →

  2. 8Negotiate and sign the lease

    Negotiate a rent-free fit-out period and a lease that matches your licence timeline. Have the tenancy agreement stamped — SFA asks for the stamp duty certificate.

    Typical lead time
    Allows 14 days to negotiate and sign. Planning estimate
    Gather
    • Letter of offer
    • Tenancy agreement
    • IRAS stamp duty certificate
    Confirm with

    Landlord

    • Rent-free period length
    • Security deposit amount
    • Handover condition and date
    • Signage rights on the shopfront

    SFA’s food shop licence application asks for the tenancy agreement and IRAS stamp duty certificate.
    Singapore Food Agency (SFA): Application process and fees for licence/permit for food retail (checked 22 Nov 2026)

Design and approvals

  1. 9Apply for change of use (if the unit is not approved for F&B)

    Applies if How much renovation does the space need? Major — bare unit or change from non-F&B use

    If the unit is not already approved for restaurant or café use, apply for URA change of use approval (and HDB approval for HDB units). Ideally confirm this before signing.

    Typical lead time
    Allows 21 days (about 10 working days’ URA processing plus preparation). HDB units can take 4 weeks or more. Planning estimate
    Gather
    • Owner’s consent
    • Floor plan
    • Description of the proposed use
    Confirm with

    Landlord

    • Owner’s written consent to the application
    • HDB approval if it is an HDB unit

    GoBusiness lists URA change of use approval at $500 with an estimated 10 working days’ processing; SLA may charge a Land Betterment Charge.
    GoBusiness Licensing (URA): Change of Use Approval — licence directory (checked 22 Nov 2026)

    HDB asks applicants to expect at least 4 weeks after all supporting documents and payment are received.
    HDB: Change of use (HDB shops and offices) (checked 22 Nov 2026)

  2. 10Design the layout and prepare the licence layout plan

    Work with your designer on the kitchen flow, counter and seating. SFA needs a scaled layout plan showing equipment, exhausts, sinks and the refreshment area boundary.

    Typical lead time
    Allows 21 days for design and drawings. Planning estimate
    Gather
    • Equipment list with sizes
    • Seating plan
    • Sink and wash-up positions
    Confirm with

    Designer

    • Scaled layout plan for SFA
    • Electrical load of all equipment
    • Exhaust and ventilation route

    SFA asks for a scaled layout plan showing equipment, exhausts, sinks and the boundary of the refreshment area.
    Singapore Food Agency (SFA): Application process and fees for licence/permit for food retail (checked 22 Nov 2026)

  3. 11Apply for the SFA food shop licence

    Apply on GoBusiness Licensing with your layout plan. Submit tenancy, change of use (if needed), cleaning programme and pest control contract within SFA’s deadline.

    Typical lead time
    Allows 21 days from application to licence, including SFA’s 7-working-day review and time to send follow-up documents. Planning estimate
    Gather
    • Scaled layout plan
    • Tenancy agreement and stamp duty certificate
    • URA/HDB approval if applicable
    • Cleaning programme
    • Pest control contract
    Confirm with

    SFA (via GoBusiness)

    • Whether an inspection is needed before you open
    • Current processing status

    SFA lists the food shop licence fee at $195, valid for one year.
    Singapore Food Agency (SFA): Application process and fees for licence/permit for food retail (checked 22 Nov 2026)

    SFA states applications are reviewed within 7 working days; the application is closed if documents are not submitted within 2 months.
    Singapore Food Agency (SFA): Application process and fees for licence/permit for food retail (checked 22 Nov 2026)

  4. 12Get landlord / management approval for fit-out plans

    Malls and many landlords must approve drawings, contractors and work hours before works start.

    Typical lead time
    Allows 14 days for landlord approval. Planning estimate
    Confirm with

    Landlord / mall management

    • Drawing approval
    • Contractor insurance and permits
    • Allowed work hours and deposits
  5. 13Check fire safety submissions with a Qualified Person

    Applies if How much renovation does the space need? Moderate — new kitchen line, plumbing, seating / Major — bare unit or change from non-F&B use

    Ask your designer or contractor whether the works need SCDF plan approval or can be lodged as minor works by a Qualified Person.

    Typical lead time
    Allows 14 days for QP review and lodgement. Planning estimate
    Confirm with

    Qualified Person (Registered Architect / PE)

    • Whether works fall under minor works or need plan approval
    • Fire safety certificate needs at completion

    SCDF states that minor works listed in its schedule do not require plan approval but are lodged by a Qualified Person (Registered Architect or Professional Engineer).
    SCDF: Minor addition and alteration works (checked 22 Nov 2026)

Fit-out

  1. 14Renovation and fit-out works

    Carpentry, plumbing, electrical, flooring, counter and seating. Keep a weekly site check and a written variation log.

    Typical lead time
    Allows 21 / 45 / 70 days for light / moderate / major works. Planning estimate
    Gather
    • Signed quotation with payment milestones
    • Work schedule
    • Variation log
    Confirm with

    Contractor

    • Completion date and late-delivery terms
    • Defects period
    • Who handles authority submissions
  2. 15Install kitchen exhaust and ventilation

    Applies if What will you prepare on site? Full hot kitchen — frying, grilling, wok

    Hot cooking needs an exhaust hood and ducting route agreed with the landlord. Long lead item — order early.

    Typical lead time
    Allows 21 days to fabricate and install. Planning estimate
    Confirm with

    Landlord

    • Approved exhaust route and discharge point

    Contractor

    • Hood size and fan capacity for your equipment
  3. 16Set up utilities, internet, waste and pest control

    Open utility accounts, book internet installation, and sign the pest control contract SFA asks for.

    Typical lead time
    Allows 14 days for installation appointments. Planning estimate

    SFA asks food shop applicants for a pest control contract and a cleaning programme.
    Singapore Food Agency (SFA): Application process and fees for licence/permit for food retail (checked 22 Nov 2026)

  4. 17Design shopfront signage and check licensing

    Signs over the exemption size need a BCA advertisement licence. Check landlord rules for size and lighting too.

    Typical lead time
    Allows 14 days for design, approval and fabrication scheduling. Planning estimate

    BCA exempts signboards totalling not more than 5m²; licence applications take about 7 working days, plus two weeks if URA must evaluate.
    BCA: Outdoor advertising sign / signboard licence application (checked 22 Nov 2026)

Equipment, suppliers and systems

  1. 18Order coffee and kitchen equipment

    Espresso machine, grinders, refrigeration, ice machine, oven, dishwasher and smallwares. Confirm power, water and drainage needs match the layout.

    Typical lead time
    Allows 30 days for ordering and delivery. Planning estimate
    Gather
    • Final equipment list
    • Power and water specs for each item
    • Delivery access and lift sizes
    Confirm with

    Equipment supplier

    • Lead time and delivery date
    • Installation and water filter
    • Warranty and service response time
    • Staff training on the machine
  2. 19Set up coffee, food and packaging suppliers

    Lock in coffee beans, milk, bakery and packaging suppliers. Arrange tastings and confirm delivery days and minimum orders.

    Typical lead time
    Allows 21 days for tastings and accounts. Planning estimate
    Gather
    • Weekly volume estimates
    • Delivery windows at your premises
    Confirm with

    Suppliers

    • Minimum order and delivery days
    • Payment terms
    • Halal status if relevant
  3. 20Set up POS, payments and checkout

    Choose a POS that fits your service style (counter, table or QR ordering), connect card and PayNow payments, and load the menu with modifiers.

    Typical lead time
    Allows 14 days to choose, configure and test, finishing 10 days before opening for staff training. Planning estimate
    Gather
    • Final menu with prices and modifiers
    • Bank account for settlement
    • Number of counters and printers
    Confirm with

    POS supplier

    • Monthly fee and contract length
    • Payment processing rates
    • Hardware cost and delivery
    • Kitchen printer or display support

People and compliance

  1. 21Recruit staff and check work pass rules

    Applies if Will you hire staff before opening? Yes

    Recruit baristas and service staff. If hiring foreign workers, check the services sector quota and levy; set up CPF for local staff.

    Typical lead time
    Allows 35 days to recruit, finishing 10 days before opening for training. Planning estimate
    Gather
    • Roles and rosters
    • Salary budget including employer CPF
    • Job descriptions

    MOM states only operators with food shop licences issued by SFA may employ migrant workers in F&B; the services sector Dependency Ratio Ceiling is 35%.
    Ministry of Manpower: Services sector requirements (Work Permit) (checked 25 Nov 2026)

    Employers pay CPF for Singapore Citizen and PR employees earning more than $50 a month.
    CPF Board: How much CPF contributions to pay (checked 25 Nov 2026)

    Hiring foreign workers: Work Permit, S Pass and EP →

  2. 22Apply for a liquor licence

    Applies if Will you sell alcohol? Yes

    Apply on GoBusiness for the liquor licence class that matches your selling hours.

    Typical lead time
    Allows 30 days for application and review (planning assumption — check current status on GoBusiness). Planning estimate
    Gather
    • Tenancy agreement
    • Layout plan
    • Planned hours of sale

    SPF lists Class 1A (sale 6am–11.59pm) at $880 and Class 1B (to 10pm) at $660; fees are non-refundable.
    Singapore Police Force: Types of liquor licences and fees (checked 22 Nov 2026)

  3. 23Complete food hygiene training

    Food handlers need the WSQ Food Safety Course Level 1. Check whether your establishment must appoint a Food Hygiene Officer.

    Typical lead time
    Allows 14 days to book and complete courses. Planning estimate
    Gather
    • Names of all food handlers
    • Course dates

    SFA requires certain licensed establishments, including canteens and cold stores, to appoint a Food Hygiene Officer (WSQ Food Safety Course Level 3).
    Singapore Food Agency (SFA): Requirements for Food Hygiene Officers (checked 22 Nov 2026)

  4. 24Arrange business insurance

    Public liability and fire/contents cover (often required by the lease), plus work injury compensation insurance for employees.

    Typical lead time
    Allows 7 days for quotes and cover. Planning estimate
    Confirm with

    Landlord

    • Minimum insurance required by the lease

    Which insurance is required, and what to consider for your sector →

Launch

  1. 25Website and pre-opening marketing

    Set up a simple website with your services or menu, prices, hours, location and booking or ordering links, so customers can find you on Google. Claim your Google Business Profile, set up social channels and delivery platforms, and plan opening offers.

    Typical lead time
    Allows 28 days of build-up before opening. Planning estimate
  2. 26Install, commission and test equipment

    Install machines, calibrate grinders, test every circuit under full load and run the POS end to end.

    Typical lead time
    Allows 7 days. Planning estimate
  3. 27Train staff and run menu trials

    Run timed service drills, finalise recipes and portioning, and check opening and closing routines.

    Typical lead time
    Allows 7 days. Planning estimate
  4. 28Soft launch

    Open to friends, family and neighbours with a limited menu. Fix bottlenecks before the public opening.

    Typical lead time
    Allows 4 days. Planning estimate
  5. 29Opening day

    First day of trade. Keep the menu tight and staff rostered generously.

Costs to budget for

Costs to budget for
UpfrontPlanning range
Security deposit (assumed 3 months’ rent)S$24,000 – S$54,000
Renovation and fit-outS$70,000 – S$150,000
Design and professional fees (designer, QP)S$5,000 – S$20,000
Coffee and kitchen equipmentS$35,000 – S$70,000
Furniture, fixtures and smallwaresS$10,000 – S$30,000
POS hardware and set-upS$1,500 – S$5,000
Registration and licence feesS$800 – S$2,500
Opening stock and packagingS$5,000 – S$12,000
Signage, branding and opening marketingS$5,000 – S$15,000
Recruitment and pre-opening wagesS$3,000 – S$10,000
Insurance (first-year premium)S$1,500 – S$4,000
MonthlyPlanning range
Rent (incl. service charge)S$8,000 – S$18,000
Staff salaries incl. employer CPFS$15,000 – S$35,000
Ingredients and packagingS$8,000 – S$20,000
Utilities and internetS$1,500 – S$3,500
POS and software subscriptionsS$100 – S$500
MarketingS$500 – S$2,500
Cleaning, pest control and wasteS$300 – S$900
Accounting and bookkeepingS$300 – S$800

Planning estimate Planning estimates by OpenReady SG, last reviewed 22 Nov 2026. They are not quotes or published prices — replace them with your own quotes.

Budget calculator →

What changes your plan

How much renovation does the space need?
Changes renovation time, fire-safety checks and fit-out costs.
What will you prepare on site?
Hot cooking adds kitchen exhaust work and raises equipment costs.
Will you sell alcohol?
Adds a liquor licence application.
Will you hire staff before opening?
Adds recruitment, CPF and work-pass checks.
What kind of premises?
Changes who approves your fit-out and which use approvals apply.