Open a childcare centre or preschool in Singapore

How to open a childcare centre or preschool in Singapore

Last reviewed: 22 Nov 2026 · Editorial standards

A preschool is one of the most regulated small businesses in Singapore. ECDA licenses every centre caring for 5 or more children under 7, sets space per child, outdoor play space, toilets and staff ratios, and requires a qualified principal and teachers before you can apply. You must not advertise or collect fees until the licence is issued. This guide puts every step in order with official sources.

Build my opening plan

~37 weeksfrom a standing start (default assumptions)
20steps
11official sources checked

Decide and register

  1. 1Choose your programmes, capacity and fees

    Decide the licence classes you need, your target capacity and fees. Capacity depends on your teaching floor space, so this drives your site search.

    Typical lead time
    Allows 14 days. Planning estimate
    Gather
    • Programmes and age groups
    • Target capacity
    • Monthly fees

    ECDA defines a preschool (ECDC) as any place that habitually cares for or teaches 5 or more children under 7 for a fee, other than by a relative or guardian of all the children.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA licenses Class A (infant care, 2–18 months), Class B (child care, 18 months to under 7) and Class C (kindergarten, up to 6 hours a day); allowed combinations are A, B, C, A+B or A+C.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    Under the Partner Operator Scheme for 2026–2030, participating centres keep monthly fees for Singapore Citizen children at or below $650 for full-day child care and $1,290 for infant care, before GST.
    Early Childhood Development Agency (ECDA): Partner Operator Scheme (POP) (checked 25 Nov 2026)

  2. 2Set your budget and enrolment ramp-up

    Fit-out and staff costs come long before full enrolment. ECDA looks at your financial capacity, so prepare a realistic budget and reserve.

    Typical lead time
    Allows 10 days. Planning estimate
    Gather
    • Funding available
    • Enrolment ramp-up by month
  3. 3Register the operating entity with ACRA

    ECDA asks for proof of the owning entity and assesses the applicant and key office-holders.

    Typical lead time
    Allows 5 days. Planning estimate
    Gather
    • Company name options
    • Directors and shareholders
    • Business address

    ECDA considers whether the applicant and key office-holders are of suitable character and fitness, past convictions and sanctions, financial capacity, and whether the applicant can occupy suitable premises.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    Not a Singapore Citizen or PR? Starting a business as a foreigner →

  4. 4Open a business bank account and bookkeeping

    Fees and subsidies are paid into a business account; keep proper records.

    Typical lead time
    Allows 14 days. Planning estimate

    How to open a business bank account →

  5. 5Check whether you must register for GST

    Compare your fee income forecast with the IRAS threshold.

    Typical lead time
    Allows 2 days. Planning estimate

    GST registration is compulsory if taxable turnover exceeds $1 million at the end of a calendar year, or is expected to in the next 12 months.
    IRAS: Do I need to register for GST? (checked 25 Nov 2026)

    GST registration and business tax basics →

Site

  1. 7Check the site can meet ECDA space rules

    Work out capacity from the teaching floor space, and check outdoor play space, toilets and the floor level before you commit.

    Typical lead time
    Allows 14 days. Planning estimate
    Confirm with

    Landlord

    • Ground floor, or ECDA approval for upper floors
    • Outdoor play space
    • Toilets and showers can be added

    ECDA calculates capacity from teaching floor space: 5m² per infant, 3m² per child for child care and 1.88m² per child for kindergarten, with each activity area at least 12m², plus a sick bay.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA requires outdoor gross-motor play space of at least 1/6 of capacity × 4m² for child care or 1/10 × 4m² for kindergarten, with a minimum of 40m²; applications without it are rejected.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA requires at least 2 toilets and 2 hand-washing points, 1 toilet and basin per 23 children, 1 shower per 50 children, and for infants 1 sink and diaper-changing table per 10 infants.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA’s prior written approval is needed if the centre is above the ground floor or in a basement.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

  2. 8Sign the tenancy

    The tenancy should be signed by the licensee and run for at least two to three years.

    Typical lead time
    Allows 14 days. Planning estimate
    Confirm with

    Landlord

    • Tenancy of 2–3 years or more in the licensee’s name
    • Rent-free period for approvals and fit-out
    • Reinstatement terms

Approvals and licence

  1. 9Get approved use for the site

    Confirm the approved use with URA or HDB. Landed houses need a URA change of use; HDB sites need HDB approval.

    Typical lead time
    Allows 7 / 14 / 30 days for commercial / HDB / landed sites. Planning estimate

    URA’s change of use fee is $500 (non-refundable) and assessment generally takes 10 working days.
    URA: Changing the use of your property (checked 25 Nov 2026)

  2. 10SCDF fire safety and building approvals

    Your Qualified Person prepares plans titled for an early childhood development centre and obtains the SCDF approvals and the Fire Safety Certificate. ECDA also needs the building’s TOP or CSC.

    Typical lead time
    Allows 30 days (planning assumption). Planning estimate

    ECDA requires an SCDF Fire Safety Certificate on a floor plan certified by a Qualified Person and titled for an ECDC; plans approved for commercial schools are not accepted.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    SCDF requires plan approval before fire safety works or a change of use affecting fire safety, submitted by a Qualified Person.
    Singapore Civil Defence Force (SCDF): Plan approval (checked 25 Nov 2026)

  3. 11Apply for the ECDA licence

    Apply on GoBusiness with your premises approvals and staff. A Licensing Officer visits the centre. You must not advertise, operate or collect money before the licence is issued.

    Typical lead time
    Allows 28 days (14 working days after documents and site visit). Planning estimate
    Gather
    • Proof of the owning entity
    • Tenancy agreement
    • Approved use, TOP/CSC and Fire Safety Certificate
    • Principal and teacher details

    ECDA states a preschool must not advertise, start operating or collect any money before it holds a valid licence; new applications are processed in 14 working days after complete documents and the site visit, whichever is later.
    Early Childhood Development Agency (ECDA): Setting up an ECDC (checked 25 Nov 2026)

    ECDA charges a $500 application and licence fee on GoBusiness, then a Licensing Officer conducts an on-site visit.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA issues licences for 6, 12, 24 or 36 months depending on the centre’s quality and compliance.
    Early Childhood Development Agency (ECDA): Choosing a preschool for your child (checked 25 Nov 2026)

    Operating a preschool without a licence can lead to a fine of up to $10,000, imprisonment of up to 12 months, or both.
    Singapore Statutes Online: Early Childhood Development Centres Act 2017, section 6 (checked 25 Nov 2026)

Fit-out

  1. 12Renovate to ECDA requirements

    Classrooms, toilets and showers, sick bay, kitchen, outdoor play area and, for infants, separate napping, feeding and diaper areas.

    Typical lead time
    Allows 30 / 60 days for moderate / major works. Planning estimate
    Confirm with

    Contractor

    • Works follow the approved plans
    • Child-safe finishes and fittings
    • Completion date

    For infant care, ECDA requires infant areas separate from older children, a separate napping area, and cots for at least half of the infants enrolled.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

  2. 13Order furniture, play equipment and learning resources

    Child-sized furniture, cots and mats, outdoor play equipment, books and learning materials.

    Typical lead time
    Allows 30 days. Planning estimate

Principal and teachers

  1. 14Appoint a qualified principal

    Recruit your principal early. ECDA must approve every staff member.

    Typical lead time
    Allows 45 days. Planning estimate

    ECDA requires a principal to be L2-certified, hold the Advanced Diploma in Early Childhood Leadership (or an approved alternative) and have at least 2 years of preschool teaching experience; all staff are approved through ONE@ECDA after a pre-employment medical.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

  2. 15Recruit teachers and educarers

    You need a minimum team before you can apply for the licence, then enough staff for ECDA’s ratios as enrolment grows.

    Typical lead time
    Allows 45 days. Planning estimate

    ECDA’s minimum staff to apply for Class B or C is a qualified principal plus at least one L2 and two L1 teachers; with infant care, an EY1 or HCIC infant carer is also needed. Trainees do not count.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA’s staff-child ratios during programme hours are 1:25 for K2, 1:20 for K1, 1:15 for Nursery, 1:12 for Pre-Nursery, 1:8 for Playgroup and 1:5 for infants.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    ECDA requires the principal and two other programme staff to hold Child First Aid certificates.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

    Employers pay CPF for Singapore Citizen and PR employees earning more than $50 a month.
    CPF Board: How much CPF contributions to pay (checked 25 Nov 2026)

    Hiring your first employee: employer checklist →

  3. 16Kitchen and cook

    Applies if Will you cook meals on site? Yes

    Hire a cook, plan menus, and confirm with SFA whether your kitchen needs a food licence.

    Typical lead time
    Allows 21 days. Planning estimate

    ECDA requires centres that serve meals to have a cook who has completed a Basic Food Hygiene Course.
    Early Childhood Development Agency (ECDA): Guide to setting up an Early Childhood Development Centre (PDF) (checked 25 Nov 2026)

  4. 17Arrange insurance

    Public liability, personal accident cover for children, contents, and work injury compensation for employees.

    Typical lead time
    Allows 10 days. Planning estimate

    Which insurance is required, and what to consider for your sector →

Systems

  1. 18Set up childcare management and parent app

    Enrolment, attendance, billing and subsidies, and parent communication.

    Typical lead time
    Allows 14 days. Planning estimate

Enrolment and launch

  1. 19Website and enrolment drive (after the licence)

    Prepare your website and materials early, but publish and advertise only once the licence is issued. Run open houses for parents.

    Typical lead time
    Allows 21 days. Planning estimate

Costs to budget for

Costs to budget for
UpfrontPlanning range
Security deposit (assumed 3 months’ rent)S$24,000 – S$75,000
Renovation to ECDA requirementsS$150,000 – S$400,000
Furniture, play equipment and resourcesS$30,000 – S$100,000
Qualified Person, SCDF and approval feesS$5,000 – S$20,000
ECDA application and licence feeS$500 – S$500
Company registration and professional feesS$500 – S$3,000
Recruitment and pre-opening salariesS$15,000 – S$50,000
Insurance (first-year premium)S$3,000 – S$10,000
Website, branding and open housesS$3,000 – S$12,000
MonthlyPlanning range
RentS$8,000 – S$25,000
Principal, teacher and staff salaries incl. CPFS$20,000 – S$60,000
Food and cookS$3,000 – S$10,000
Utilities and internetS$1,000 – S$3,000
Childcare management softwareS$100 – S$600
Learning materials and consumablesS$800 – S$3,000
Accounting and bookkeepingS$500 – S$1,500

Planning estimate Planning estimates by OpenReady SG, last reviewed 22 Nov 2026. They are not quotes or published prices — replace them with your own quotes.

Budget calculator →

What changes your plan

Which programmes will you run?
ECDA licenses infant care (Class A), child care (Class B) and kindergarten (Class C) separately, each with its own space and staff rules.
Where will the centre be?
URA needs no planning permission for childcare in commercial buildings and HDB void decks, but landed houses need a change of use.
Will you cook meals on site?
Centres serving meals need a cook trained in food hygiene.
How much renovation does the site need?
Preschool fit-outs need toilets, sick bay and play areas sized to your capacity.

Official sources