Open a foot massage or reflexology shop in Singapore

How to open a foot massage or reflexology shop in Singapore

Last reviewed: 22 Nov 2026 · Editorial standards

Foot massage is massage under Singapore law, and there is no longer a foot reflexology exemption. From 1 Dec 2026 open-concept shops need a Category 3 licence, and hiring foreign reflexologists needs a Category 1 licence with CaseTrust accreditation. Location is the other big constraint: URA does not support massage businesses in a list of exclusion areas, and HDB foot reflexology shops must be open concept. This guide puts every step in order with official sources.

Build my opening plan

~17 weeksfrom a standing start (default assumptions)
24steps
14official sources checked

Decide and register

  1. 1Define your services, prices and layout

    Decide your service menu and whether you will run an open-concept shop or have rooms. This decides your licence category, premises size and who you can hire.

    Typical lead time
    Allows 7 days. Planning estimate
    Gather
    • Service menu with duration and price
    • Open concept or rooms
    • Target customers and opening hours

    The Massage Establishments Act defines massage as rubbing, kneading or manipulating the human body or any part of it, for purposes such as relaxing muscle tension or stimulating circulation.
    Singapore Statutes Online: Massage Establishments Act 2017 (checked 25 Nov 2026)

    The current Massage Establishments (Exemption) Order has no exemption for foot reflexology; it exempts only cases such as licensed healthcare premises, massage by registered TCM practitioners, allied health professionals or doctors, head or scalp massage only, and customers below 12.
    Singapore Statutes Online: Massage Establishments (Exemption) Order 2018 (checked 25 Nov 2026)

  2. 2Set your budget, funding and break-even

    Use the budget tool to separate fit-out, chairs and licences from rent and wages.

    Typical lead time
    Allows 7 days. Planning estimate
    Gather
    • Funding available
    • Break-even customers per day
  3. 3Register your business with ACRA

    Register through Bizfile. The Police licence applicant must be at least 21 and fit and proper.

    Typical lead time
    Allows 3 days. Planning estimate
    Gather
    • Business name options
    • Owner details
    • Business address
    • SSIC activity description

    ACRA lists a one-year sole proprietorship registration at $115 ($15 name application plus $100 registration).
    ACRA: Choosing a business structure (checked 22 Nov 2026)

    SPF requires the massage establishment licensee to be at least 21 years old at the time of application, fit and proper, and to hold a valid work pass if a foreigner.
    Singapore Police Force: Apply for a massage establishment licence (checked 22 Nov 2026)

    Not a Singapore Citizen or PR? Starting a business as a foreigner →

  4. 4Open a business bank account and bookkeeping

    Keep package prepayments and takings in a business account.

    Typical lead time
    Allows 14 days. Planning estimate

    How to open a business bank account →

  5. 5Check whether you must register for GST

    Compare your revenue forecast with the IRAS threshold.

    Typical lead time
    Allows 2 days. Planning estimate

    GST registration is compulsory if taxable turnover exceeds $1 million at the end of a calendar year, or is expected to in the next 12 months.
    IRAS: Do I need to register for GST? (checked 25 Nov 2026)

    GST registration and business tax basics →

Premises

  1. 7Check the unit before you sign

    Check water points and drainage for foot basins, hot water, ventilation, and that the layout can meet your licence category.

    Typical lead time
    Allows 7 days. Planning estimate
    Confirm with

    Landlord

    • Water and hot water supply
    • Ventilation and air-conditioning
    • Permission for your layout (open concept or rooms)
    • Reinstatement at lease end
  2. 8Negotiate and sign the lease

    Make sure the permitted use covers massage or foot reflexology, and allow enough rent-free time for licensing.

    Typical lead time
    Allows 14 days. Planning estimate
    Confirm with

    Landlord

    • Permitted use clause
    • Rent-free period long enough for licensing
    • Deposit and signage rights

Licences and approvals

  1. 9Design a layout that meets your licence category

    Open-concept shops must keep every massage visible from inside and outside, with no rooms or partitions. Shops with rooms must meet the floor area for their category.

    Typical lead time
    Allows 10 days. Planning estimate

    SPF’s Category 3 conditions require full public visibility, no obscuring devices, and no private rooms or partitions, whether foldable, low-height or otherwise.
    Singapore Police Force: Massage establishment licence FAQ (PDF) (checked 25 Nov 2026)

    SPF’s framework sets a minimum floor area of 100 m² for Category 1 and 50 m² for Category 2, and Category 2 is generally not allowed in HDB premises.
    Singapore Police Force: Massage establishments regulatory framework (PDF) (checked 25 Nov 2026)

  2. 10Apply for the Police massage establishment licence

    Apply for the licence category that matches your layout. Each employee also needs Police approval. Do not start operating before the licence is issued.

    Typical lead time
    Allows 30 days (SPF states approximately 4 weeks for Category 1 and 2). Planning estimate
    Gather
    • Layout plan
    • URA or HDB approval for the premises
    • Details of each employee

    SPF states that from 1 Dec 2026 open-concept massage establishments are no longer exempt and need a new Category 3 licence ($340 for 3 years or $510 for 5 years); existing operators have a grace period to 30 Nov 2027.
    Singapore Police Force: Apply for a massage establishment licence (checked 22 Nov 2026)

    SPF lists Category 1 and 2 licence fees from 1 Dec 2026 at $290 for 1 year, $630 for 3 years and $980 for 5 years; new licensees first get a one-year provisional licence.
    Singapore Police Force: Apply for a massage establishment licence (checked 22 Nov 2026)

    SPF’s Category 3 FAQ sets operating hours of 7.00 am to 10.30 pm daily and states existing open-concept operators who apply before 1 Jun 2027 pay a concession fee of $170 (3 years) or $255 (5 years).
    Singapore Police Force: Massage establishment licence FAQ (PDF) (checked 25 Nov 2026)

    Operating a massage establishment without a licence can lead to a fine of up to $10,000, imprisonment of up to 2 years, or both (higher for repeat offenders).
    Singapore Statutes Online: Massage Establishments Act 2017 (checked 25 Nov 2026)

  3. 11Get landlord approval for fit-out

    Submit drawings and contractor details before works start.

    Typical lead time
    Allows 10 days. Planning estimate
  4. 12Plan CaseTrust accreditation for a Category 1 licence

    Applies if Will you hire foreign therapists? Yes

    Hiring foreign therapists needs a Category 1 licence, which requires CaseTrust accreditation (with one year to obtain it on a provisional licence) and at least 100 m².

    Typical lead time
    Allows 30 days to start the process (planning assumption). Planning estimate

    MOM states that to hire a foreigner as a masseur, spa therapist, foot reflexologist or manicurist, you must first obtain a Category 1 massage establishment licence.
    Ministry of Manpower: Requirements to hire a foreigner to provide massage services (checked 25 Nov 2026)

    SPF’s framework requires CaseTrust accreditation for Category 1, with one year to obtain it under a provisional Category 1 licence.
    Singapore Police Force: Massage establishments regulatory framework (PDF) (checked 25 Nov 2026)

Fit-out

  1. 13Renovation and fit-out

    Flooring, plumbing for foot basins, lighting, air-conditioning and reception, built to your approved layout.

    Typical lead time
    Allows 10 / 25 / 40 days for light / moderate / major works. Planning estimate
    Confirm with

    Contractor

    • Completion date
    • Layout matches licence conditions
    • Defects period
  2. 14Signage and Police poster

    Design signage within landlord rules. Licensed shops must display the Police poster; larger signs may need a BCA licence.

    Typical lead time
    Allows 10 days. Planning estimate

    BCA exempts signboards totalling not more than 5m²; licence applications take about 7 working days, plus two weeks if URA must evaluate.
    BCA: Outdoor advertising sign / signboard licence application (checked 22 Nov 2026)

Equipment and systems

  1. 15Order reflexology chairs and equipment

    Reflexology chairs or recliners, foot basins, towel warmers, linen, trolleys and storage.

    Typical lead time
    Allows 21 days. Planning estimate
    Confirm with

    Equipment supplier

    • Lead time
    • Warranty
    • Cleaning requirements for basins
  2. 16Set up bookings, POS and payments

    Walk-in queue and booking management, packages, staff commissions and card or PayNow payments.

    Typical lead time
    Allows 10 days. Planning estimate

People and compliance

  1. 17Recruit therapists and get Police approval for each

    Applies if Will you hire therapists before opening? Yes

    Recruit therapists and apply for Police approval for every employee. Check the nationality rules for your licence category before hiring.

    Typical lead time
    Allows 35 days. Planning estimate

    SPF’s framework allows only Singapore citizens, permanent residents and Malaysians with valid work permits for categories other than Category 1; Category 1 has no restriction on foreigners, subject to MOM approval.
    Singapore Police Force: Massage establishments regulatory framework (PDF) (checked 25 Nov 2026)

    SPF requires Category 1 and 2 employees, from 1 Dec 2026, to wear a sleeved top showing the establishment’s name or logo and the employee’s name, with knee-length or longer pants.
    Singapore Police Force: Apply for a massage establishment licence (checked 22 Nov 2026)

    Employers pay CPF for Singapore Citizen and PR employees earning more than $50 a month.
    CPF Board: How much CPF contributions to pay (checked 25 Nov 2026)

    Hiring your first employee: employer checklist →

  2. 18Set hygiene routines for basins, towels and chairs

    Clean and disinfect foot basins between customers, use fresh towels, and train every therapist.

    Typical lead time
    Allows 5 days. Planning estimate

    HealthHub publishes guidance for barbers, hairdressers and beauticians on preventing blood-borne infections.
    HealthHub: Guidance for barbers, hairdressers and beauticians (checked 22 Nov 2026)

  3. 19Arrange insurance

    Public liability, treatment liability, contents cover, and work injury compensation for employees.

    Typical lead time
    Allows 7 days. Planning estimate

    Which insurance is required, and what to consider for your sector →

Launch

  1. 20Website and pre-opening marketing

    Set up a simple website with your services, prices, opening hours, location and booking, so customers can find you on Google.

    Typical lead time
    Allows 21 days. Planning estimate
  2. 21Install and test

    Check hot water at every basin, chair positions against your approved layout, and the booking flow.

    Typical lead time
    Allows 3 days. Planning estimate
  3. 22Staff training and trial sessions

    Run trial sessions with friends after the licence is issued, check timing and hygiene routines.

    Typical lead time
    Allows 5 days. Planning estimate
  4. 23Soft launch

    Open with limited hours to test flow before the full launch.

    Typical lead time
    Allows 4 days. Planning estimate

Costs to budget for

Costs to budget for
UpfrontPlanning range
Security deposit (assumed 3 months’ rent)S$10,500 – S$27,000
Renovation and plumbingS$8,000 – S$20,000
Reflexology chairs, basins and equipmentS$6,000 – S$25,000
Massage establishment licence and employee approvalsS$400 – S$1,500
Booking, POS and tablet set-upS$500 – S$2,500
Registration and enquiry feesS$200 – S$1,000
Signage, branding and launch marketingS$2,000 – S$8,000
Recruitment and pre-opening wagesS$1,500 – S$5,000
Insurance (first-year premium)S$1,000 – S$3,000
MonthlyPlanning range
Rent (incl. service charge)S$3,500 – S$9,000
Therapist wages and commissions incl. employer CPFS$6,000 – S$20,000
Oils, creams, towels and consumablesS$400 – S$1,500
Utilities and internetS$600 – S$1,500
Booking and software subscriptionsS$50 – S$300
MarketingS$500 – S$2,000
Laundry and cleaningS$300 – S$900
Accounting and bookkeepingS$300 – S$700

Planning estimate Planning estimates by OpenReady SG, last reviewed 22 Nov 2026. They are not quotes or published prices — replace them with your own quotes.

Budget calculator →

What changes your plan

What layout will your shop have?
Open-concept shops need the new Category 3 licence; shops with rooms or partitions need Category 1 or 2.
Will you hire foreign therapists?
MOM requires a Category 1 licence before you can hire foreign foot reflexologists.
What kind of premises?
HDB and commercial buildings have different approval routes and location limits.
How much renovation does the unit need?
Changes renovation time and cost.
Will you hire therapists before opening?
Every employee needs Police approval under your licence.